Canadian Site Visit and Workshop - Summary and International Perspective
Canadian Site Visit and Workshop - Summary and International Perspective
Socio-Technical Challenges to Implementing Geological Disposal: a Synthesis of Findings from 14 Countries
Socio-Technical Challenges to Implementing Geological Disposal: a Synthesis of Findings from 14 Countries
This report aims to clarify the dynamics of socio-technical challenges in the implementation of geological disposal (GD) for High Level Waste (HLW) and Spent Nuclear Fuel (SNF). Drawing on the 14 country reports produced within InSOTEC’s WP1 the synthesis focuses on socio-technical challenges that appear across national contexts. The synthesis report elucidates issues made visible through bringing together the analyses of different national contexts.
INITIAL SCREENING FOR SITING A DEEP GEOLOGICAL REPOSITORY FOR CANADA'S USED NUCLEAR FUEL - Northern Village of Pinehouse, Saskatchewan
INITIAL SCREENING FOR SITING A DEEP GEOLOGICAL REPOSITORY FOR CANADA'S USED NUCLEAR FUEL - Northern Village of Pinehouse, Saskatchewan
On August 17, 2010, the Northern Village of Pinehouse, Saskatchewan and the Kineepik Métis Local expressed interest in learning more about the Nuclear Waste Management Organization (NWMO) site selection process to find an informed and willing community to host a deep geological repository for Canada’s used nuclear fuel (NWMO 2010). This report summarizes the findings of an initial screening, conducted by Golder Associates Ltd., to evaluate the potential suitability of the Pinehouse area against five screening criteria using readily available information.
INITIAL SCREENING FOR SITING A DEEP GEOLOGICAL REPOSITORY FOR CANADA'S USED NUCLEAR FUEL - Corporation of the Township of Huron-Kinloss
INITIAL SCREENING FOR SITING A DEEP GEOLOGICAL REPOSITORY FOR CANADA'S USED NUCLEAR FUEL - Corporation of the Township of Huron-Kinloss
On April 16, 2012, the Corporation of the Township of Huron-Kinloss expressed interest in learning more about the Nuclear Waste Management Organization (NWMO) site selection process to find an informed and willing community to host a deep geological repository for Canada’s used nuclear fuel (NWMO, 2010). This report summarizes the findings of an initial screening, conducted by AECOM, to evaluate the potential suitability of the Township of Huron-Kinloss against five screening criteria using readily available information.
INITIAL SCREENING FOR SITING A DEEP GEOLOGICAL REPOSITORY FOR CANADA'S USED NUCLEAR FUEL - Municipality of Brockton, Ontario
INITIAL SCREENING FOR SITING A DEEP GEOLOGICAL REPOSITORY FOR CANADA'S USED NUCLEAR FUEL - Municipality of Brockton, Ontario
On January 9, 2012 the Corporation of the Municipality of Brockton expressed interest in learning more about the Nuclear Waste Management Organization (NWMO) site selection process to find an informed and willing community to host a deep geological repository for Canada’s used nuclear fuel (NWMO, 2010). This report summarizes the findings of an initial screening, conducted by AECOM., to evaluate the potential suitability of the Municipality of Brockton against five initial screening criteria using readily available information.
INITIAL SCREENING FOR SITING A DEEP GEOLOGICAL REPOSITORY FOR CANADA'S USED NUCLEAR FUEL - City of Elliot Lake
INITIAL SCREENING FOR SITING A DEEP GEOLOGICAL REPOSITORY FOR CANADA'S USED NUCLEAR FUEL - City of Elliot Lake
On March 12, 2012, the City of Elliot Lake expressed interest in learning more about the Nuclear Waste Management Organization (NWMO) site selection process to find an informed and willing community to host a deep geological repository for Canada’s used nuclear fuel (NWMO, 2010). This report summarizes the findings of an initial screening, conducted by Geofirma Engineering Ltd., to evaluate the potential suitability of the City of Elliot Lake against five screening criteria using readilyavailable information.
INITIAL SCREENING FOR SITING A DEEP GEOLOGICAL REPOSITORY FOR CANADA'S USED NUCLEAR FUEL - Town of Spanish
INITIAL SCREENING FOR SITING A DEEP GEOLOGICAL REPOSITORY FOR CANADA'S USED NUCLEAR FUEL - Town of Spanish
On March 21, 2012, the Town of Spanish expressed interest in learning more about the Nuclear Waste Management Organization (NWMO) site selection process to find an informed and willing community to host a deep geological repository for Canada’s used nuclear fuel (NWMO, 2010). This report summarizes the findings of an initial screening, conducted by Geofirma Engineering Ltd., to evaluate the potential suitability of the Town of Spanish against five screening criteria using readily available information.
INITIAL SCREENING FOR SITING A DEEP GEOLOGICAL REPOSITORY FOR CANADA'S USED NUCLEAR FUEL - Corporation of the Municipality of South Bruce
INITIAL SCREENING FOR SITING A DEEP GEOLOGICAL REPOSITORY FOR CANADA'S USED NUCLEAR FUEL - Corporation of the Municipality of South Bruce
On, March 27, 2012, the Corporation of the Municipality of South Bruce expressed interest in learning more about the Nuclear Waste Management Organization (NWMO) site selection process to find an informed and willing community to host a deep geological repository for Canada’s used nuclear fuel (NWMO, 2010). This report summarizes the findings of an initial screening, conducted by AECOM, to evaluate the potential suitability of the Municipality of South Bruce against five screening criteria using readily available information.
INITIAL SCREENING FOR SITING A DEEP GEOLOGICAL REPOSITORY FOR CANADA'S USED NUCLEAR FUEL - Township of Red Rock
INITIAL SCREENING FOR SITING A DEEP GEOLOGICAL REPOSITORY FOR CANADA'S USED NUCLEAR FUEL - Township of Red Rock
On February 25, 2011, the Township of Red Rock expressed interest in learning more about the Nuclear Waste Management Organization (NWMO) site selection process to find an informed and willing community to host a deep geological repository for Canada’s use d nuclear fuel (NWMO, 2010). This report presents the findings of an initial screening, conducted by Golder Associates Ltd., to evaluate the potential suitability of the Red Rock area against five initial screening criteria using readily available information.
Report on NWMO-First Nations Quebec and Labrador Sustainable Development Institute Project, Discussion Project between the First Nations and the NWMO
Report on NWMO-First Nations Quebec and Labrador Sustainable Development Institute Project, Discussion Project between the First Nations and the NWMO
Expansion of the Repository for Spent Nuclear Fuel: Environmental Impact Assessment Report
Expansion of the Repository for Spent Nuclear Fuel: Environmental Impact Assessment Report
Safety Case Plan
Safety Case Plan
Following the guidelines set forth by the Ministry of Trade and Industry (now Ministry of Employment and Economy) Posiva is preparing to submit the construction license application for a spent fuel repository by the end of the year 2012. The long-term safety section supporting the license application is based on a safety case, which, according to the internationally adopted definition, is a compilation of the evidence, analyses and arguments that quantify and substantiate the safety and the level of expert confidence in the safety of the planned repository.
Final Disposal of Spent Nuclear Fuel in Olkiluoto
Final Disposal of Spent Nuclear Fuel in Olkiluoto
Olkiluoto Site Description
Olkiluoto Site Description
This second version of the Olkiluoto Site Report, produced by the OMTF (Olkiluoto Modelling Task Force), updates the Olkiluoto Site Report 2004 (Posiva 2005) with the data and knowledge obtained up to December 2005.<br/>The main product of the modelling has been to develop a descriptive model of the site (the Site Descriptive Model), i.e. a model describing the geometry, properties of the bedrock and the water and the associated interacting processes and mechanisms.
Final Disposal of Spent Nuclear Fuel in Finnish Bedrock - Kivetty Site Report
Final Disposal of Spent Nuclear Fuel in Finnish Bedrock - Kivetty Site Report
Posiva Oy is studying the Finnish bedrock for the geological disposal of spent nuclear fuel. The study is based on the site selection research programme started originally in 1983. The programme is in accordance with the decision in principle by the Council of State in 1983 and aims at the selection of one site in 2000. Four sites, Hastholmen in Loviisa, Kivetty in Aanekoski, Olkiluoto in Eurajoki and Romuvaara in Kuhmo, have been studied in detail. This report summarises the results of the site investigations carried out at Kivetty.
Final Disposal of Spent Nuclear Fuel in Finnish Bedrock - Olkiluoto Site Report
Final Disposal of Spent Nuclear Fuel in Finnish Bedrock - Olkiluoto Site Report
Posiva Oy is studying the Finnish bedrock for the geological disposal of spent nuclear fuel. The study is based on the site selection research programme started originally in 1983. The programme is in accordance with the decision in principle by the Council of State in 1983 and aims at the selection of one site in 2000. Four sites, Hastholmen in Loviisa, Kivetty in Aanekoski, Olkiluoto in Eurajoki and Romuvaara in Kuhmo, have been studied in detail. This report summarises the results of the site investigations carried out at Olkiluoto.
Final Disposal of Spent Nuclear Fuel in Finnish Bedrock - Romuvaara Site Report
Final Disposal of Spent Nuclear Fuel in Finnish Bedrock - Romuvaara Site Report
Posiva Oy is studying the Finnish bedrock for the geological disposal of spent nuclear fuel. The study is based on the site selection research programme started originally in 1983. The programme is in accordance with the decision in principle by the Council of State in 1983 and aims at the selection of one site in 2000. Four sites, Hastholmen in Loviisa, Kivetty in Aanekoski, Olkiluoto in Eurajoki and Romuvaara in Kuhmo, have been studied in detail. This report summarises the results of the site investigations carried out at Romuvaara.
Interim Summary Report of the Safety Case
Interim Summary Report of the Safety Case
The report outlines the current design and safety concept for the planned repository. It summarises the approach used to formulate scenarios for the evolution of the disposal system over time, describes these scenarios and presents the main models and computer codes used to analyse them. It also discusses compliance with Finnish regulatory requirements for long-term safety of a geological repository and gives the main evidence, arguments and analyses that lead to confidence, on the part of Posiva, in the long-term safety of the planned repository
Summary of National and International Radioactive Waste Management Programs 1979
Summary of National and International Radioactive Waste Management Programs 1979
Many nations and international agencies are working to develop improved technology and industrial capability for nuclear fuel cycle and waste management operations. The effort in some countries is limited to research in university laboratories on treating low-level waste from reactor plant operations.
Fourth Review Meeting of the Joint Convention on the Safety of Spent Fuel Management and on the Safety of Radioactive Waste Management, Canada's Responses to Questions to its Fourth National Report
Fourth Review Meeting of the Joint Convention on the Safety of Spent Fuel Management and on the Safety of Radioactive Waste Management, Canada's Responses to Questions to its Fourth National Report
Fourth Review Meeting of the Joint Convention on the Safety of Spent Fuel Management and on the Safety of Radioactive Waste Management, Canada's Responses to Questions to its Fourth National Report
The Final Disposal Facility for Spent Nuclear Fuel
The Final Disposal Facility for Spent Nuclear Fuel
Thorough long-term studies have shown that the Finnish bedrock is suitable for the permanent isolation of spent nuclear fuel from organic nature. Legislation requires that besides safety, an assessment be made of any other environmental impacts of the final disposal facility. Environmental impact assessment (EIA) in respect of the final disposal facility for spent nuclear fuel got under way in 1997 when Posiva Oy, which is responsible for the project, began work on an EIA programme.
Posiva Annual Report
Posiva Annual Report
Main events Licensing process proceeds according to plan Posiva aims to submit the construction license application in 2012. In 2011, research and analysis work continued to ensure the timely availability of results and related reports. The feedback provided by the Radiation and Nuclear Safety Authority and other authorities for the preliminary licensing documentation submitted in 2009 was systematically reviewed in 2011, and steps were taken to ensure it is taken into account during the license submission phase.