Skip to main content

Nuclear Waste: Operation of Monitored Retrievable Storage Facility is unlikely by 1998

DOE requested $100 million over the next 3 years to develop an MRS facility by 1998. DOE can begin accepting delivery of utilities’ waste by 1998 only by having an MRS facility then. To accomplish this, however, the Nuclear Waste Negotiator must complete a siting agreement and obtain congressional approval of the agreement, including the removal of statutory links to repository development, by the end of 1992. The negotiator does not believe this is possible.<br/><br/>Whether DOE is legally obligated to store or dispose of waste in 1998 is unclear.