Siting Experience Documents Only
Country
Keywords
Treatment and final disposal of nuclear waste: Programme for encapsulation, deep geological disposal, and research, development and demonstration: Ch 1 - 5
Treatment and final disposal of nuclear waste: Programme for encapsulation, deep geological disposal, and research, development and demonstration: Ch 1 - 5
In RD&D-Programme 92, SKB presented a partially new strategy for its activities. The new strategy entailed a focusing and concentration on the implementation of deep disposal of a limited quantity (about 800 tonnes) of encapsulated spent nuclear fuel during the coming 20-year period. Following this initial deposition, the results of the work will be evaluated, and only then will a decision be taken as to how and when regular deposition of the main body of the fuel and other long-lived nuclear waste will take place.
Site selection - Siting of the Final Repository for Spent Nuclear Fuel
Site selection - Siting of the Final Repository for Spent Nuclear Fuel
SKB has selected Forsmark as the site for the final repository for spent nuclear fuel. The site selection<br/>is the end result of an extensive siting process that began in the early 1990s. The strategy and<br/>plan for the work was based on experience from investigations and development work over a period<br/>of more than ten years prior to then.<br/>This document describes the siting work and SKB’s choice of site for the final repository.
RD&D-Programme 2001 Programme for research, development and demonstration of methods for the management and disposal of nuclear waste
RD&D-Programme 2001 Programme for research, development and demonstration of methods for the management and disposal of nuclear waste
The preceding RD&D-Programme from 1998 was supplemented in December 2000 by an integrated account of method, site selection and programme prior to the site<br/>investigation phase. Since the latter account lies close in time, SKB has chosen to<br/>concentrate RD&D-Programme 2001 on research and technology development. Viewpoints<br/>offered on previous RD&D-programmes and comments from the review of the<br/>SR 97 safety assessment comprise important input for RD&D-Programme 2001.
Integrated account of method, site selection and programme prior to the site investigation phase
Integrated account of method, site selection and programme prior to the site investigation phase
In order to dispose of the spent nuclear fuel in a safe manner, SKB plans to site<br/>a deep repository and an encapsulation plant with associated canister fabrication<br/>and transportation system. After an integrated evaluation of feasibility studies<br/>and other material, SKB will proceed with investigations of the rock and studies<br/>regarding establishment of the deep disposal system in the municipality of<br/>Oskarshamn or in Northern Uppland.
Handling and final disposal of nuclear waste. September 1989
Handling and final disposal of nuclear waste. September 1989
For those parts of the waste system that have already been taken into operation - transportation and handling systems, central interim storage facility for spent nuclear fuel (CLAB) and final repository for reactor waste (SFR)- the research and development stage has already largely been passed. The programme presented here therefore pertains primarily to the treatment and final disposal of spent fuel and the decommissioning of nuclear power plants.
Demonstration and Dialogue: Mediation in Swedish Nuclear Waste Management
Demonstration and Dialogue: Mediation in Swedish Nuclear Waste Management
This report analyses mediation and mediators in Swedish nuclear waste management. Mediation is about establishing agreement and building common knowledge. It is argued that demonstrations and dialogue are the two prominent approaches to mediation in Swedish nuclear waste management. Mediation through demonstration is about showing, displaying, and pointing out a path to safe disposal for inspection. It implies a strict division between demonstrator and audience.
Expert Judgement in Performance Assessment
Expert Judgement in Performance Assessment
Proposals to site, construct and operate a radioactive waste disposal facility in Sweden will be supported by performance assessments (PAs). Such PAs will require a range of expert judgements to be made. As part of SKI’s preparation for reviewing SKB’s Pas and for conducting independent PAs, SKI has identified a need for further research on the treatment of expert judgement in PA.
Public Values and Stakeholder Involvement - A New Framework for Performance Assessment
Public Values and Stakeholder Involvement - A New Framework for Performance Assessment
The objective of the RISCOM II project is to share the knowledge of the context of radioactive waste management in various European countries and to see to what extent it is possible to apply more widely the RISCOM Model (Andersson et al., 1998) in order to improve the acceptability of radioactive waste management. Thus, the project aims to promote the development of processes involving transparency, as well as means involving greater participation of the public.
Foreign Programs for the Storage of Spent Nuclear Power Plant Fuels, High-Level Waste Canisters and Transuranic Wastes
Foreign Programs for the Storage of Spent Nuclear Power Plant Fuels, High-Level Waste Canisters and Transuranic Wastes
Worldwide activities related to the storage of spent (irradiated) nuclear power reactor fuel and highly-radioactive, long-lived wastes are summarized, with a review of the storage programs and plans of 26 nations. The focus of the report is on the application of dry storage techniques to spent fuel, although dry storage of long-lived wastes is also reviewed.
From Risk Analysis to the Safety Case. Values in Risk Assessments
From Risk Analysis to the Safety Case. Values in Risk Assessments
The foundation for work related to nuclear waste management is laid by laws and outlines e.g. the responsibilities of the reactor owners and the state, as represented by the authorities. The Swedish Nuclear Fuel and Waste Management Company (SKB), as well as Posiva Oy in Finland, were set up by the reactor owners in the respective countries in response to the responsibilities of planning, conducting research and to implement the physical structures leading to a safe management of nuclear wastes.
Review of initiatives addressing socio-technical challenges of RWM & geological disposal in international programmes
Review of initiatives addressing socio-technical challenges of RWM & geological disposal in international programmes
Reflecting on the Implementing Geological Disposal Technology Platform as a knowledge network and potential scenarios for stakeholder involvement
Reflecting on the Implementing Geological Disposal Technology Platform as a knowledge network and potential scenarios for stakeholder involvement
This report was prepared in the context of Work Package 3 of the InSOTEC project. The overall objective of this work package (WP) is to take a closer look at arenas where socio-technical combinations on radioactive waste management (RWM) are formed. The attempt is to illustrate the interconnections between the sources of different types of information and knowledge development with the various stakeholders having access to that information.
Geological Problems in Radioactive Waste Isolation Second Worldwide Review Part 2 Ch 10 - 17
Geological Problems in Radioactive Waste Isolation Second Worldwide Review Part 2 Ch 10 - 17
The first world wide review of the geological problems in radioactive waste isolation was published by Lawrence Berkeley National Laboratory in 1991. This review was a compilation of reports that had been submitted to a workshop held in conjunction with the 28th International Geological Congress that took place July 9-19,1989 in Washington, D.C.
Geological Problems in Radioactive Waste Isolation Second Worldwide Review Part 3 Ch 18 -27
Geological Problems in Radioactive Waste Isolation Second Worldwide Review Part 3 Ch 18 -27
The first world wide review of the geological problems in radioactive waste isolation was published by Lawrence Berkeley National Laboratory in 1991. This review was a compilation of reports that had been submitted to a workshop held in conjunction with the 28th International Geological Congress that took place July 9-19,1989 in Washington, D.C.
Identifying remaining socio-technical challenges at the national level: France
Identifying remaining socio-technical challenges at the national level: France
France isn’t only a country known for its cheese… it’s also a country of nuclear power. With its 58 nuclear reactors (63,000 megawatts), producing 79% of the country’s electricity, France is arguably the world’s leader in the production of nuclear energy. It is estimated that the relative contribution of nuclear energy to power production in France will decline to 70% in 2020 - the main reason for this being governmental investments into renewable energies.
Performance Assessment, Participative Processes and Value Judgements: Report from the First RISCOM II Workshop
Performance Assessment, Participative Processes and Value Judgements: Report from the First RISCOM II Workshop
Articles of the Planning Act N¡. 2006-739 of 28 June 2006 Concerning the Sustainable Management of Radioactive Materials and Waste modifying the Environmental Code.
Articles of the Planning Act N¡. 2006-739 of 28 June 2006 Concerning the Sustainable Management of Radioactive Materials and Waste modifying the Environmental Code.
Frances Planning Act for Radioactive Materials and Waste
Quality of Decision-making Processes: Decision-making processes in Radioactive Waste Governance - Insights and Recommendations WP3
Quality of Decision-making Processes: Decision-making processes in Radioactive Waste Governance - Insights and Recommendations WP3
Work Package 3 (WP 3) set out to provide practical recommendations for the design and implementation of a “robust” decision-making process (DMP) in radioactive waste governance/governance of radioactive waste management (RWG).
Structuring local communities and development of local democracy for engagement in Radioactive Waste Management governance
Structuring local communities and development of local democracy for engagement in Radioactive Waste Management governance
Strong Local Support for Final Repository
Strong Local Support for Final Repository
Local support in favor of a final repository for spent nuclear in one's own municipality has increased somewhat in both Oskarshamn and Östhammar. This is shown by the annual public opinion poll that was conducted by Synovate on behalf of SKB.
Radioactive Waste Management Programmes in OECD/NEA Member Countries: Sweden
Radioactive Waste Management Programmes in OECD/NEA Member Countries: Sweden
Summary of radioactive waste and management programs in Sweden, including national nuclear energy context; sources, types, and quantities of waste; radioactive waste management policies and programs; research and development; decommissioning and dismantling policies and projects; transport; authorities and implementing organizations; financing; and public information.
A Site is Selected
A Site is Selected
Web page from SKB's website (Swedish Nuclear Fuel and Waste Management Company), announcing that it has selected Forsmark, in the municipality of Östhammar, as the site for the final repository for Sweden's spent nuclear fuel.
Continuing Cooperation with Two Municipalities
Continuing Cooperation with Two Municipalities
Web page from SKB's website (Swedish Nuclear Fuel and Waste Management Company) discussing the ongoing cooperation between SKB and both Östhammar, where the repository is to be sited, and Oskarshamn, where the encapsulation plant is to be located.
The Cigéo Project: Meuse/Haute-Marne Reversible Geological Disposal Facility for Radioactive Waste
The Cigéo Project: Meuse/Haute-Marne Reversible Geological Disposal Facility for Radioactive Waste
Report prepared by ANDRA, the French National Radioactive Waste Management Agency, for preparing for public debate in 2013.