Spent Nuclear Fuel Management: How centralized interim storage can expand options and reduce costs

The purpose of this study is to assist decision makers in evaluating the centralized interim
storage option. We explore the economics of centralized interim storage under a wide variety of
circumstances. We look at how a commitment to move forward with centralized interim storage
today could evolve over time. And, we evaluate the costs of reversing a commitment toward
centralized storage if it turns out that such a decision is later considered a mistake. We have not

Disposal and Storage of Spent Nuclear Fuel — Finding the Right Balance

The Nuclear Waste Policy Act of 1982, as amended, established a statutory basis
for managing the nation’s civilian (or commercially produced) spent nuclear
fuel. The law established a process for siting, developing, licensing, and constructing
an underground repository for the permanent disposal of that waste.
Utilities were given the primary responsibility for storing spent fuel until it is
accepted by the Department of Energy (DOE) for disposal at a repository —
originally expected to begin operating in 1998. Since then, however, the repository

Nuclear Waste: Is There A Need For Federal Interim Storage?

About 20,000 metric tons of spent, or used, nuclear
fuel have accumulated since the beginning of commercial
nuclear power prbduction in the United States. At the end
of the currently licensed period of all existing nuclear power
plants and those under construction, the amount of spent
nuclear fuel is expected to total 87,000 metric tons.
Thus far, practically all of the spent nuclear fuel is
stored in water-filled pools at reactor sites. However, space
does not exist in the pools to store all the spent fuel expected

The Problem of used nuclear fuel: lessons for interim solutions from a comparative cost analysis

An acceptable long-term solution for used (spent) fuel from nuclear power reactors has evaded all countries engaged in the civilian
nuclear fuel cycle. Furthermore, many countries are trying to develop interim storage solutions that address the shortage of storage in
the spent fuel cooling pools at reactors. The United States has a particularly acute problem due to its adherence to an open fuel cycle
and its large number of reactors. Two main options are available to address the spent fuel problem: dry storage on-site at reactors and

Revisiting America's Nuclear Waste Policy

With the first 100 days of the Obama Administration behind us, the Institute for 21st Century Energy presents
this nuclear waste policy document that recounts the history of the country’s nuclear waste policy, discusses
the mechanics of the issue, and off ers specifi c recommendations to the Obama Administration and the
U.S. Congress.
Two weeks aft er the 2008 presidential election, the Institute released dozens of energy policy recommendations for
the incoming administration and 111th Congress. Ten recommendations focused on committing to and expanding

Interim Storage of Spent Nuclear Fuel A Safe, Flexible, and Cost-Effective Near-Term Approach to Spent Fuel Management

The management of spent fuel from nuclear power
plants has become a major policy issue for virtually every
nuclear power program in the world. For the nuclear industry, finding sufficient capacity for storage and processing or
disposal of spent fuel is essential if nuclear power plants are
to be allowed to continue to operate. At the same time, the
options chosen for spent fuel management can have a substantial impact on the political controversies, proliferation
risks, environmental hazards, and economic costs of the

Dedicated-site, interim storage of high-level nuclear waste as part of the management system

Dedicated-site interim storage of high-level reprocessed nuclear waste and of spent fuel rods is proposed as a long-term integral part of the systems approach of the national nuclear waste isolation program. Separation of interim sites for retrievable storage from permanent-disposal repositories should enhance ensurance of the performance of the latter; maintenance of retrievability at separate sites also has many advantages in both safety and possible use of waste as resources.

Consolidated Interim Storage of Commercial Spent Nuclear Fuel

Approximately 54,000 tons of spent nuclear fuel are stored at operating nuclear power
plants and several decommissioned power plants throughout the country. Spent fuel
storage at these sites was never intended to be permanent. The current Federal plan is to
place the fuel in a repository for permanent disposal in Nevada at Yucca Mountain.
Recently, appropriations committees in Congress suggested building one or more Federal
sites for consolidated interim storage of spent fuel. Several reasons were identified. The

Disclaimer: Note that this page contains links to external sites. When leaving the CURIE site, please note that the U.S. Department of Energy and Pacific Northwest National Laboratory do not control or endorse the content or ads on these sites.