Technical Evaluation Report on the Content of the U.S. Department of Energy's Yucca Mountain Repository License Application
Technical Evaluation Report on the Content of the U.S. Department of Energy's Yucca Mountain Repository License Application
This “Technical Evaluation Report on the Content of the U.S. Department of Energy’s Yucca Mountain License Application; Postclosure Volume: Repository Safety After Permanent Closure” (TER Postclosure Volume) presents information on the NRC staff’s review of DOE’s Safety Analysis Report (SAR), provided on June 3, 2008, as updated by DOE on February 19, 2009. The NRC staff also reviewed information DOE provided in response to NRC staff’s requests for additional information and other information that DOE provided related to the SAR.
slides - Cumulative Impact of Industry and NRC Actions
slides - Cumulative Impact of Industry and NRC Actions
Presented at the NEI Used Fuel Management Conference, St. Petersburg, FL, May 7-9, 2013
Disposal Subcommittee Report to the Full Commission
Disposal Subcommittee Report to the Full Commission
The Disposal Subcommittee of the Blue Ribbon Commission on America’s Nuclear Future (BRC) addressed a wide-ranging set of issues, all bearing directly on the central question: “How can the United States go about establishing one or more disposal sites for high-level nuclear wastes in a manner and within a timeframe that is technically, socially, economically, and politically acceptable?”
NRC/NEI, January 24, 2014 Public Meeting Presentations
NRC/NEI, January 24, 2014 Public Meeting Presentations
NRC/NEI, January 24, 2014 Public Meeting Presentations
Slides - Retrievability, Cladding Integrity, and Safety Handling during Storage and Transportation
Slides - Retrievability, Cladding Integrity, and Safety Handling during Storage and Transportation
Presented at the NEI Used Fuel Management Conference, St. Petersburg, FL, May 7-9, 2013
NRC Waste Confidence Rulemaking, Federal Register, 1984, 1990, 1999, and 2008
NRC Waste Confidence Rulemaking, Federal Register, 1984, 1990, 1999, and 2008
NRC Waste Confidence Rulemaking, Federal Register, 1984, 1990, 1999, and 2008
Yucca Mountain Licensing Standard Options for Very Long Time Frames: Technical Bases for the Standard and Compliance Assessments
Yucca Mountain Licensing Standard Options for Very Long Time Frames: Technical Bases for the Standard and Compliance Assessments
In the existing U.S. Environmental Protection Agency (EPA) and Nuclear Regulatory Commission (NRC) regulations governing the spent nuclear fuel and high-level radioactive waste site at Yucca Mountain, Nevada, the time period of compliance was set at 10,000 years. Recently, a Court ordered that EPA and NRC either revise the regulation on this topic to be "based upon and consistent with" recommendations made by a panel of the National Academy of Sciences, who recommended a time period of compliance out to as long as one million years, or seek congressional relief.
Disposal Subcommittee Report to the Full Commission DRAFT
Disposal Subcommittee Report to the Full Commission DRAFT
The Disposal Subcommittee of the Blue Ribbon Commission on America’s Nuclear Future has
commenced to address a set of issues, all of which bear directly on the central question: “How can the
United States go about establishing one or more disposal sites for high-level nuclear wastes in a manner
and within a timeframe that is technically, socially, economically, and politically acceptable?”
To answer this question and to develop specific recommendations and options for consideration by the
Factors Affecting Public and Political Acceptance for the Implementation of Geological Disposal
Factors Affecting Public and Political Acceptance for the Implementation of Geological Disposal
The main objective of this report is to identify conditions which affect public concern (either
increase or decrease) and political acceptance for developing and implementing programmes
for geologic disposal of long-lived radioactive waste. It also looks how citizens and relevant
actors can be associated in the decision making process in such a way that their input is
enriching the outcome towards a more socially robust and sustainable solution. Finally, it
aims at learning from the interaction how to optimise risk management addressing needs and
Overview of the Nuclear Regulatory Commission and Its Regulatory Process for the Nuclear Fuel Cycle for Light Water Reactors
Overview of the Nuclear Regulatory Commission and Its Regulatory Process for the Nuclear Fuel Cycle for Light Water Reactors
This paper provides a brief description of the United States Nuclear Regulatory Commission (NRC) and its regulatory process for the current nuclear fuel cycle for light water power reactors (LWRs). It focuses on the regulatory framework for the licensing of facilities in the fuel cycle. The first part of the paper provides an overview of the NRC and its regulatory program including a description of its organization, function, authority, and responsibilities.
Comparing Nuclear Fuel Cycle Options
Comparing Nuclear Fuel Cycle Options
The comparison of different nuclear fuel cycle options has become an integral element to any analysis of the future prospects for nuclear energy, in the United States and around the world. Concerns for supply security and price volatility of fossil fuels, combined with growing resolve to reduce the emissions of greenhouse gases, have caused a general shift in attitudes towards nuclear energy. However, there are lingering sustainability concerns for nuclear energy – long term uranium supply and environmental impact – as well as concerns about the proliferation of nuclear weapons.
Blue Ribbon Commission on America’s Nuclear Future Draft Report to the Secretary of Energy
Blue Ribbon Commission on America’s Nuclear Future Draft Report to the Secretary of Energy
America’s nuclear waste management program is at an impasse. The Obama Administration’s decision
to halt work on a repository at Yucca Mountain in Nevada is but the latest indicator of a policy that has
been troubled for decades and has now all but completely broken down. The approach laid out under
the 1987 Amendments to the Nuclear Waste Policy Act (NWPA)—which tied the entire U.S. high-level
waste management program to the fate of the Yucca Mountain site—has not worked to produce a
slides - Industry Response to NRC's Request for Comments on Retrievability, Cladding Integrity and 10 CFR 71/72 Alignment
slides - Industry Response to NRC's Request for Comments on Retrievability, Cladding Integrity and 10 CFR 71/72 Alignment
Presented at the NEI Used Fuel Management Conference, St. Petersburg, FL, May 7-9, 2013
slides - Generic Communications and Guidance on Spent Fuel Storage & Transportation
slides - Generic Communications and Guidance on Spent Fuel Storage & Transportation
Presented at the NEI Used Fuel Management Conference, St. Petersburg, FL, May 7-9, 2013
Key Issues Associated with Interim Storage of Used Nuclear Fuel
Key Issues Associated with Interim Storage of Used Nuclear Fuel
The issue of interim storage of used (spent)1 fuel is dependent on a number of key factors, some
of which are not known at this time but are the subject of this study. The first is whether or not
the Yucca Mountain Project continues or is cancelled such that it may be able to receive spent
fuel from existing and decommissioned nuclear power stations. The second is whether the United
States will pursue a policy of reprocessing and recycling nuclear fuel. The reprocessing and
Commercial Nuclear Waste: Effects of a Termination of the Yucca Mountain Repository Program and Lessons Learned
Commercial Nuclear Waste: Effects of a Termination of the Yucca Mountain Repository Program and Lessons Learned
DOE decided to terminate the Yucca Mountain repository program because, according to DOE officials, it is not a workable option and there are better solutions that can achieve a broader national consensus. DOE did not cite technical or safety issues. DOE also did not identify alternatives, but it did create a Blue Ribbon Commission to evaluate and recommend alternatives.
Draft Report for Comment: Identification and Prioritization of the Technical Information Needs Affecting Potential Regulation of Extended Storage and Transportation of Spent Nuclear Fuel
Draft Report for Comment: Identification and Prioritization of the Technical Information Needs Affecting Potential Regulation of Extended Storage and Transportation of Spent Nuclear Fuel
he U.S. Nuclear Regulatory Commission (NRC) regulates storage of spent nuclear fuel (SNF) from commercial nuclear power plants. An increasing amount of the SNF in storage is in dry storage systems, mostly at current and decommissioned plants. As directed by the Commission (in SRM-COMSECY-10-0007; December 6, 2010), in expectation of continued use of dry storage for extended periods of time, the NRC staff is examining the technical needs and potential changes to the regulatory framework that may be needed to continue licensing of SNF storage over periods beyond 120 years.
Nuclear Energy Research and Development Roadmap
Nuclear Energy Research and Development Roadmap
To achieve energy security and greenhouse gas (GHG) emission reduction objectives, the United States must develop and deploy clean, affordable, domestic energy sources as quickly as possible. Nuclear power will continue to be a key component of a portfolio of technologies that meets our energy goals. This document provides a roadmap for the Department of Energy’s (DOE’s) Office of Nuclear Energy (NE) research, development, and demonstration activities that will ensure nuclear energy remains viable energy option for the United States.
Waste Control Specialists / NRC pre-application public meeting slides
Waste Control Specialists / NRC pre-application public meeting slides
These slides were presented by Waste Control Specialists LLC (WCS) to the NRC at the June 16, 2015 pre-application public meeting at the NRC offices in Rockville, Maryland.
NRC SFST ISG-2: Fuel Retrievability
NRC SFST ISG-2: Fuel Retrievability
This Interim Staff Guidance (ISG) provides guidance to the staff for determining if
storage systems to be licensed under 10 CFR Part 72 allow ready retrieval of spent fuel.
This guidance is not a regulation or a requirement.
NRC ISG-1: Classifying the Condition of Spent Nuclear Fuel for Interim Storage and Transportation Based on Function
NRC ISG-1: Classifying the Condition of Spent Nuclear Fuel for Interim Storage and Transportation Based on Function
This Interim Staff Guidance (ISG) provides guidance to the staff on classifying spent nuclear
fuel as either (1) damaged, (2) undamaged, or (3) intact, before interim storage or
transportation. This is not a regulation or requirement and can be modified or superseded by
an applicant with supportable technical arguments.
Revision 2
NRC SFST ISG-3: Post Accident Recovery and Compliance with 10 CFR 72.122(l)
NRC SFST ISG-3: Post Accident Recovery and Compliance with 10 CFR 72.122(l)
Compliance with 10 CFR 72.122(l) has been interpreted to mean that a licensee, during any
point in the storage cycle, must have a means of retrieving and repackaging individual fuel
assemblies even after an accident. The staff has reevaluated this interpretation.
NRC SFST ISG-4: Cask Closure Weld Inspections
NRC SFST ISG-4: Cask Closure Weld Inspections
The closure weld for the outer cover plate for austenitic stainless steel designs may be
inspected using either volumetric or multiple pass dye penetrant techniques subject to the
following conditions:
• Dye penetrant (PT) examination may only be used in lieu of volumetric
examination only on austenitic stainless steels. PT examination should be done
in accordance with ASME Section V, Article 6, “Liquid Penetrant Examination.”
• For either ultrasonic examination (UT) or PT examination, the minimum
NRC SFST ISG-5: Confinement Evaluation
NRC SFST ISG-5: Confinement Evaluation
Several changes have occurred since the issuance of NUREG-1536, “Standard Review Plan
(SRP) for Dry Cask Storage Systems,” that affect the staff’s approach to confinement
evaluation. The attachment to this ISG integrates the current staff approach into a revision of
ISG-5. The highlights of the changes include:
• Reflects October 1998 revisions to 10 CFR 72.104 and 10 CFR 72.106.
• Expands and clarifies acceptance criteria associated with confinement analysis and
acceptance of “leak tight” testing instead of detailed confinement analysis.